Dee Why RSL Club

Stage 4 Refurbishment

The Dee Why RSL Club Stage 4 Refurbishment involved extensive works throughout the majority of existing areas of the Club. The Club remained operational throughout the duration of the works and which was carried out over 14 months in 4 stages. The works involved the refurbishment of the Club’s Bistro, kitchen and bars, Café, L3 Functions Rooms & Auditorium, installation of a new goods lift and escalators, extension to the building façade spanning 4 floors creating a new Pre-function area, basement plantrooms and Alfresco Gaming areas.


Client

Dee Why RSL

Architect

Altis Architecture

Contract sum

$16m

Program

60 weeks

Completion

January 2014