Defence Maintenance Management

Fit-out

DMM’s fit-out was accommodated within an existing commercial building and Buildcorp Interiors’ scope of works included the cut-out and construction of an interconnecting stair to create easy access and interaction between their three tenanted levels. A large proportion of the fit-out consisted of an open plan workstation environment supported by the built environment of offices, meeting rooms and breakout areas. Custom designed joinery within the fit-out and the external deck area provided DMM with a successfully socially interactive environment.


Client

Defence Material Organisation

Architect

Gray Puksand

Contract sum

$6.5m

Program

16 weeks

Completion

December 2010