Productivity Commission

A 2040m2 office fitout in the newly completed Melbourne Quarter 2 building

Buildcorp were appointed the project in September 2020 and completed

the single level 2040m2 fitout in December 2020.

The fitout scope of works included:

  • Plasterboard and glazed partitions
  • Feature ceilings
  • Floor coverings
  • Joinery
  • Fixtures and fittings
  • Operable wall
  • Modifications to existing base building services
  • Managing all aspects of the delivery and installation of workstations and AV.

Client

Commonwealth Government Agency (Productivity Commission)

Architect

Siren Design

Contract sum

$3.0m

Program

13 weeks

Completion

December 2020