Redlands Senior Campus

Multi-stage project within an operational school campus

This multi-stage project heralds the first stage of the Redlands Senior Campus Master Plan. Buildcorp was engaged as an Early Contractor Involvement (ECI) contractor for 12 weeks to develop a plan to progress the site. This process also de-risked the project by providing price and program certainty for the remaining works.

  • Stage 1 of the project was the construction of a new five storey New Learning Hub featuring flexible learning spaces, new links, courtyards and outdoor learning spaces, an accessible rooftop with gardens and a 55 space basement carpark.
  • Stage 2 of the project included approx. 3,500m2 of outdoor landscaped spaces. These multipurpose spaces were built over the top of existing classrooms and the new carpark.
  • Stage 3 of the project completed in April 2021 and included major infrastructure improvements, services upgrades and a new internal access road complete with bus parking bay and landscaping.

Stakeholder management
Redlands School is located in a bustling residential community hub and the project has a wide range of local and internal stakeholders to consider. The project team developed a comprehensive communication plan to manage the stakeholder groups throughout the construction.


Client

SCECGS Redlands Limited

Architect

TDK Architects

Contract sum

$38.8m

Program

92 weeks

Completion

April 2021