Loreto Normanhurst New Boarding School

Normanhurst NSW 2076

Buildcorp_educationaccomm_newbuild_Loreto_1920x951
Client
Loreto Normanhurst
Architect
AJC
Project Manager
Carmichael Tompkins Property Group
Program
ECI phase: 12 months
Main works phase: 19 months
Completion
December 2025 (anticipated)
Contract Sum
$37.5m

Initially engaged through an ECI phase, Buildcorp worked closely with the client, consultants and key stakeholders from the school to provide value management, design finalisation, buildability and program advice before transitioning into main works.

Spanning more than 12 months, the ECI phase allowed Buildcorp’s project team to add value early in the process which facilitated a smooth and seamless transition to the construction phase, ultimately enabling the school to maintain operational continuity and ensure curricula, classes and exams are able to progress as planned.

The new purpose-built Boarding School will deliver increased student accommodation for over 200 students with a variety of room configurations, flexible common spaces, updated accommodation for boarding staff and will reflect the school’s vision to create a modern, accessible and ecologically sustainable home for boarding students. The new state-of-the-art Boarding School has been designed with the needs of current and future Loreto Normanhurst boarders in mind, whilst also enhancing the experience for day students and the community through carefully considered communal spaces.

This innovative space will be located on Mount Pleasant Avenue, and will span four levels, cascading down the slope beside the gymnasium. It will have an outlook across the oval and will feature a range of communal areas that will also improve the on campus experience for day students.

Buildcorp_educationaccomm_newbuild_Loreto_1920x1398
Buildcorp_educationaccomm_newbuild_Loreto_1920x1080-min

Services & Sectors

New build construction of a new state-of-the-art Boarding School spanning four levels to provide an additional 216 beds for boarding students with a variety of room configurations including six bed dorms for younger boarders, as well as two bed and single bed rooms for senior students. It will also include common and communal areas, including a lounge, shared dining/study spaces, BBQ terrace, cafeteria and cooking facilities. Practical completion is due in late 2025.

New Build

View Projects

Accommodation

View Projects

Education

View Projects
We’re with you.

Considering partnering with us?

Send us a message below and one of our team members will be in touch.

buildcorp-project-4